Project

Some of Projects Details

Mumbai Metro line - 3 Package 2 (L&T)

Mumbai Metro line - 3 Package 1 (L&T)

Western Railway (Mahalaxmi)

Mumbai Metro line - 3 Package 7 (L&T)

May 12, 2022/

About Mahalaxmi Railway Station: Mahalaxmi whose station code is ‘MX’, also spelled-as Mahalakshmi, is a railway station on the Western…

Our Project Details

Rig .No OwnerAsset DetailsManufacturing YearMachine Sr. No.Engine Sr. No
1Eastman InfrastructurePiling Rig Mait HR 1302006HR-1302991032BEJ11075
2Eastman InfrastructurePiling Rig Mait HR 1802007HR1802511233MBD08547
3Eastman InfrastructurePiling Rig Mait HR 1802008HR1802940630MBD06891
4Eastman InfrastructurePiling Rig Mait HR 1302009HR1303901130JRA01137
5Eastman InfrastructurePiling Rig Mait HR 1302009HR1303971137JRA01385
6Eastman InfrastructurePiling Rig MAI CAT 18020091800331223C3N00296
7Eastman InfrastructurePiling Rig Mait HR 1302011HR-13074F0724JTF09295
8Eastman InfrastructurePiling Rig Mait HR 1302008HR-1303660527JRA00770
9Eastman InfrastructurePiling Rig Mait HR 1802008HR-1803440216REH15102
10Eastman InfrastructurePiling Rig Mait HR 1802008HR-1803321052MBD08149
11Eastman InfrastructurePiling Rig Mait HR 1302007HR-1303200529BEJ11086
12Eastman InfrastructurePiling Rig Mait HR 1302006HR-1302880506BEJ14469
13Eastman InfrastructurePiling Rig Mait HR 1802018HR-1802AC2530REH09363
14Eastman InfrastructurePiling Rig Mait HR 1802018HR-1802AR2511REH09364
15Eastman InfrastructurePiling Rig Mait HR 1802018HR-1804EX2924REH09397
16Eastman InfrastructurePiling Rig Mait HR 1802018HR-1804NM0916REH09422
17Eastman InfrastructurePiling Rig Mait HR 1802018HR-1804SF0821REH10690
18Eastman InfrastructurePiling Rig Mait HR 300 - 5702017HR3001KR0132.MCW09354
19Eastman InfrastructurePiling Rig Mait HR 1802017HR-1802KW0630REH07940
20Eastman InfrastructurePiling Rig Mait HR 1802017HR-1802BM2613REH07800
21Eastman InfrastructurePiling Rig Mait HR 1802015HR-1809DX2632REH05285

Our Other Project Details

SR.NONAME OF CLIENTSSITEPROJECT COST
1B.G.SHIRKE CON.TECHNO.PVT LTDVIRAR SITE1,43,01,607
2B.G.SHIRKE CON.TECHNO.PVT LTDSION SITE82,09,705
3B.G.SHIRKE CON.TECHNO.PVT LTDPUNE SITE1,92,80,986
4B.G.SHIRKE CON.TECHNO.PVT LTDCENTURY MILL WORLI SITE30,39,237
5LARSEN & TOUBRO LTD.ANDHERI AIRPORT SITE1,18,39,969
6LARSEN & TOUBRO LTD.MUMBAI INTERNATIONAL AIRPORT SITE32,42,500
7LARSEN & TOUBRO LTD.Churchgate Site3,15,06,953
8LARSEN & TOUBRO LTD.Hutatma Site7,22,23,340
9LARSEN & TOUBRO LTD.Marol & MIDC Site9,26,96,130
10AHLUWALIA CO.INDIA LTD.ANDHERI VERSOVA10,07,85,384
11HOUSING DEVELOPMENT INFRASTRUCTURE PVT LTDKURLA-KAMANI1,90,60,516
12HOUSING DEVELOPMENT INFRASTRUCTURE PVT LTDANDHERI-VERSOVA10,20,275
13ITD CEMENTATION INDIA LTDCHATTISGARH SITE1,98,03,536
14IVRCL INFRASTRUCTURE AND PROJECTS LIMITEDMUNDRA , GUJARAT SITE1,35,92,698
15ERA INFRA ENGINEERING LTDBHEL ANPARA UP SITE1,50,64,705
16PIPAVAV SHIPYARD LTD.PIPAVAV – GUJARAT1,51,68,388
17PUNJ LIOYD LTD.BANGLORE-METRO69,00,000
18R.K.MADANI & CO.URAN SITE29,62,864
19RELCON INFRAPROJECTS.BANDRA-MMRDA33,33,136
20SUPREME INFRASTRUCTURE INDIA LTDBHIWANDI SITE39,00,000
21SEW INFRASTRUCTURE.ANDHERI METRO66,72,062
22DHAVAL DEVELOPERSCHARKOPE KANDIVALI SITE1,43,30,244
23DEV ENGINEERSDADAR WESTERN RAILWAY1,01,68,242
24R.K. MADHANI & COMPANYDADAR WESTERN RAILWAY1,05,70,907
25BHARAT INFRASTRUCTURE & ENGINEERING PVT LTDMADUVAN ANDHERI SITE1,17,88,336
26SATRA PROPERTIES (I) . LTDGHATKOPAR & KANJURMARG SITE1,08,92,778
27UNIVERSAL DEVELOPERSBHANDUP SITE2,13,77,026
28MAYFAIR HOUSING PVT LTDANDHERI SITE51,73,984
29MAYFAIR HOUSING PVT LTDSANTACRUZ SITE29,87,754
30DHEERAJ HOUSING PVT LTDBANDRA D-MONTE SITE93,25,015
31DBM GEOTECHNICS & CONSTRUCTIONS PVT LTD.ANDHERI ALFA SITE29,94,467
32KEYSTONE BSS LTD.ANDHERI METRO18,00,000
33TEN CONSTRUCTION(I) PVT LTDANIK WADALA SITE18,00,000
34J.KUMAR INFRAPROJECTS PVT LTDAndheri Metro Project43,74,972
35MAYFAIR HOUSING PVT LTDAKSHAY SITE29,87,754
36UCT DEVELOPERSKHAR SITE25,00,000
37LAKDAWALA DEVELOPERS PVT LTDSION KOLIWADA20,00,000
38HCC –MMS JOINT VENTUREAzad Maidan18,88,000
39HCC –MMS JOINT VENTUREGrant Road1,02,66,000
40Tata Projects- CGPL MundraGujarat8,31,00,000
41Tata Projects- BTRS - DadarMumbai3,16,00,000
42Reliance – Astaldi –JV Mumbai Metro Line 4Mumbai8,90,00,000